What to check before handover, room by room and outside. Use it as a starting point and add the checks your project, specification and client need.

Before you start

  • Have the current drawings with you, so you can check against the latest revision.
  • Work in the same order in every room: ceiling, walls, windows, doors, floor, then fittings and services.
  • Take a photo of every snag, and note exactly where it is.
  • Check in good light. A torch held low across a wall shows up marks and uneven finishes.

Walls and ceilings

  • Paint finish: even colour, no runs, patches, brush marks or missed areas.
  • Plaster and board: no cracks, dents, nail pops or visible joints.
  • Corners and edges straight and clean; beads not damaged.
  • Tiling: even joints, no cracked or loose tiles, grout and silicone complete.
  • Ceilings level, with access panels, grilles and fittings neatly finished.

Floors

  • Floor finishes level, clean and undamaged, with no lifting edges.
  • Thresholds and trims fitted where floor finishes meet.
  • Skirting fitted tight, with joints filled and painted.

Doors and ironmongery

  • Doors open and close freely, without catching or swinging on their own.
  • Even gaps around the door; closers adjusted.
  • Handles, locks and hinges fitted firmly and working; keys present.
  • Fire doors fitted with the signs, seals and closers set out in the specification.
  • Frames and architraves undamaged and finished.

Windows

  • Windows open, close and lock properly; restrictors fitted where needed.
  • Glass clean and undamaged, with labels and film removed.
  • Seals, sills and reveals complete and finished.

Kitchens and bathrooms

  • Units level and secure, doors and drawers aligned and working.
  • Worktops undamaged, joints sealed.
  • Taps, showers and toilets working, with no leaks.
  • Silicone neat and complete around baths, basins and worktops.
  • Extract fans working.

Electrics and services

  • Sockets, switches and fittings straight, with covers fitted.
  • Lights working, including emergency lighting where fitted.
  • Heating and hot water working; radiators secure and free of leaks.
  • Labels and test certificates provided for the handover information.

Outside

  • Brickwork and pointing clean and complete, with no mortar staining.
  • Gutters, downpipes and roof finishes complete.
  • Paths, paving and parking finished, with no trip hazards.
  • External lighting, fencing, gates and landscaping complete.
  • Site cleared of materials and rubbish.

After the walk-round

Give each snag to the trade responsible, with a date to fix it by, then check each fix and close it. See how to write a good snag and what goes in a snagging report.